Agenda Item No. V. A. 2. a.
Washburn University Board of Regents
SUBJECT: Petro Allied Health Landscape Improvement - Project No. P-0113
DESCRIPTION:
Bids were received on December 12, 2002 for the installation of the landscape plan for the east side of Petro Allied Health Building. Bids were as follows:
| Contractor | Base Bid | Days to Complete |
| Blackburn Nursery |
$175,564.00 |
640 | |
| Lawrence Landscape, Inc. |
$139,515.00 |
165 | |
| Herynk's Greenhouse | No Bid Submitted | |
| Luxury Lawn & Landscape | No Bid Submitted | |
| Skinner Garden Store | No Bid Submitted | |
FINANCIAL IMPLICATIONS:
Expenditure of $139,515.00 from Capital Improvement Account #03-00302.
RECOMMENDATION:
President Farley recommends the Board of Regents approve award of contract to Lawrence Landscape, Inc. for $139,515.00 for the installation of the landscape plan at Petro Allied Health Building.
________________________ _______________________
(date) Jerry B. Farley, President