Agenda Item No. _______________
Washburn University Board of Regents
SUBJECT: Change Orders - Memorial Union
DESCRIPTION:
The following change orders, which modify the contract of the contractor, are recommended.
General Contract - McPherson Contractors, Inc.
2. PR-24, PCO-32: Modify exterior handrail returns. A net increase of $1,024.00 was approved by the Board at its December 2001 meeting. Subsequent to the meeting, the architect agreed to pay for this modification. Net decrease: ($1,024.00).
3. PCO-37: Miscellaneous electrical work requested by the owner. Net increase: $707.00.
4. PCO-38: Relocate mop sink to Storage-118 (where floor machine will be stored). Net increase: $2,192.00.
Net contract change: Increase: $1,875.00
No change contract completion date - February 28, 2002
Contract - Star Signs & Graphics, Inc.
6. Add two (2) 1'-11" x 13" menu boards in Corner Store. Net increase: $2,210.00.
7. Add one (1) 1'-7" x 13" menu board for Union Market. Net increase: $1,025.00.
8. Add three (3) 13" x 20" M-1 type menu boards for Union Market. Net increase: $780.00.
Net contract change: Increase: $4,015.00
No change contract completion date - February 28, 2002
FINANCIAL IMPLICATIONS:
Net increase in project cost of $5,890.00. Total commitment from contingency including this request is $99,332, leaving a $280,321 contingency balance.
RECOMMENDATION:
President Farley recommends approval of the change orders by the Board of Regents.
______________________ _____________________________________
Date Jerry B. Farley, President