Agenda Item No. _______________

Washburn University Board of Regents

SUBJECT: Change Orders Living Learning Center Project





DESCRIPTION:





The following change orders, which modify the contracts of the three prime contractors, are recommended.





General Contract McPherson Contractors, Inc.



1. Additional kitchen equipment for Stauffer Commons food court. Net increase: $15,930.00.

Net contract change: Increase: $15,930.00

No change contract completion date - June 26, 2001



Electrical Contract Torgeson Electric

1. Move transformer TD3 to Janitor's Room #235 and move panel LD3 to east wall of closet #200A. Net increase: $5,567.24.

2.Provide labor and materials associated with additional kitchen equipment for Stauffer Commons food court. Net increase: $9,102.41.

3.Add one (1) working day to contract for item 1.

4.Add one (1) working day to contract for item 2.

Net contract change: Increase: $14,669.65

New contract completion date June 20, 2001

FINANCIAL IMPLICATIONS:



Net increase in project cost of $30,599.65. Total commitment from contingency including this request is $287,569, leaving a $235,226 contingency balance.



RECOMMENDATION:



President Farley recommends approval of the change orders by the Board of Regents.





______________________ _____________________________________

Date Jerry B. Farley, President


[ WU Home ] [ Directory ] [ A-Z Index ] [ Sitemap ] [ Contact WU ] [ Statements & Disclosures ] [ Accessibility ] [ Search ]
© 2014 Washburn University, 1700 SW College Ave, Topeka, Kansas 66621 (785) 670-1010
Contact webmaster@washburn.edu with questions or comments.