Agenda Item No.
Washburn University Board of Regents
SUBJECT: Change Orders Living Learning Center Project
DESCRIPTION:
The following change orders, which modify the contracts of the three prime contractors, are recommended.
General Contract McPherson Contractors, Inc.
1. Deduct for revisions to comply with plan review ($6,605.50)
2. Deduct for savings in equal but less costly roof deck ($10,000.00)
3. Add for removal of Carruth piers (approved by Board chair) $2,222.00
4. Add for change in wall construction of tower $4,887.25
Net Contract Change Deduct ($9,496.25)
No change in contract time Completion Date June 6, 2001
Mechanical Contract Piping Contractors
1. Add for revisions to comply with plan review $16,715.49
2. Deduct for dampers not required in review ($4,000.00)
3. Deduct for controls not required ($1,457.00)
4. Deduct for change in pipe sizing ($997.00)
Net Contract Change Add $10,261.49
Two days added to contract time Completion Date June 7, 2000
Electrical Contract Torgeson Electric
1. Add for revisions to comply with plan review $9,187.02
2. Deduct for damper controls not required in review ($1,200.00)
3. Add for grounding conductor required by code $2,711.73
Net Contract Change Add $10,698.75
No change in contract time Completion Date June 5, 2000
FINANCIAL IMPLICATIONS: Net increase in project cost of $11,463.99. Total commitment from contingency including this request is $68,451, leaving a $454,344 contingency balance.
RECOMMENDATION: President Farley recommends approval of the change orders by the Board of Regents.
________________________ _______________________________________
(date) Jerry B. Farley, President