Agenda Item No. _______________

Washburn University Board of Regents

SUBJECT: Change Orders Living Learning Center Project





DESCRIPTION:





The following change orders, which modify the contracts of the three prime contractors, are recommended.





General Contract McPherson Contractors, Inc.



1. Provide sprinkler sleeves under drives and walks for future irrigation system that were deleted when original landscaping alternate was not taken. Net increase: $3,091.35.

2.Additional 12" wide soffits at upper floors of Bldg. 1. Net increase: $8,500.00. (Approved by Board June 13, 2001 meeting.) The $8,500.00 was an estimate: actual costs for this change was $7,499.00 with results in a net decrease of $1,001.00.

Net contract change: Increase: $2,090.35

No change contract completion

date for Bldgs. 1 and 2 - June 27, 2001

No change contract completion date

for Bldg. 3 - July 11, 2001



FINANCIAL IMPLICATIONS:



Net increase in project cost of $2,090.35. Total commitment from contingency including this request is $325,133, leaving a $197,662 contingency balance.



RECOMMENDATION:



President Farley recommends approval of the change orders by the Board of Regents.





______________________ _____________________________________

Date Jerry B. Farley, President


[ WU Home ] [ Directory ] [ A-Z Index ] [ Sitemap ] [ Contact WU ] [ Statements & Disclosures ] [ Accessibility ] [ Search ]
© 2014 Washburn University, 1700 SW College Ave, Topeka, Kansas 66621 (785) 670-1010
Contact webmaster@washburn.edu with questions or comments.