Agenda Item No. _______________
Washburn University Board of Regents
SUBJECT: Change Orders - Living Learning Center Project
DESCRIPTION:
The following change orders, which modify the contracts of the three prime contractors, are recommended.
General Contract - McPherson Contractors, Inc.
Add for expansion of building number three (approx. 1,500 sq.ft.) for food court expansion. $112,664.00
Deduct for change in grade and cut of wood doors from grade AA to grade A with rift cut veneers. Species to remain white oak. ($12,619.00)
Deduct to delete latex additive specified for mortar for the installation of the stone veneer. ($19,500.00)
Add for beams, revise beam sizes, to raise the mechanical mezzanine in building number three by two feet to accommodate food court expansion. ($2,035.00)
Net contract change: Add $82,580.00
Ten working days added to contract time - Completion date June 20, 2001.
Mechanical Contract - Piping Contractors
Add for expansion of building number three (approx. 1,500 sq.ft.) for food court expansion. $6,810.00
Net contract change: Add $6,810.00
Four working days added to contract time - Completion date June 12, 2001.
Electrical Contract - Torgeson Electric
Add for expansion of building number three (approx. 1,500 sq.ft.) for food court
expansion. $1,411.66
Net contract change: Add $1,411.66
No change in contract time - Completion date June 5, 2001.
FINANCIAL IMPLICATIONS:
Net increase in project cost of $90,801.66. Total commitment from contingency including this request is $159,253, leaving a $363,542 contingency balance.
RECOMMENDATION:
President Farley recommends approval of the change orders by the Board of Regents.
______________________ _____________________________________
Date Jerry B. Farley, President