Agenda Item No. _______________
Washburn University Board of Regents
SUBJECT: Change Orders - Living Learning Center Project
DESCRIPTION:
The following change orders, which modify the contracts of the three prime contractors, are recommended.
General Contract - McPherson Contractors, Inc.
Delete windows, provide stud infill. Add hoist beams and guide rail beams in elevator shafts. Net increase: $2,459.00
Change fire extinguisher cabinets to stainless steel finish. Increase motor horsepower to increase speed in elevators of building one. Net increase: $2,814.00
Change west and east poured concrete walls of building two to 8" reinforced CMU walls. Change from colored mortar mix to white sand cement. Net decrease: ($3,590.00)
Add upper doors, frames to closets in single unit suites. Door hardware: accept base bid and alternates 1 and 3, add pincode pad at 114 doors, and hardware installation. Net decrease: ($16,874.00)
Net contract change: Decrease: ($15,191.00)
No change in contract time - Completion date June 20, 2001.
Electrical Contract - Torgeson Electric
Add two door hold opens and a smoke detector. Net increase: $935.66
Net contract change: Add $935.66
No change in contract time - Completion date June 5, 2001.
FINANCIAL IMPLICATIONS:
Net decrease in project cost of ($14,255.34). Total commitment from contingency including this request is $144,998, leaving a $377,797 contingency balance.
RECOMMENDATION:
President Farley recommends approval of the change orders by the Board of Regents.
______________________ _____________________________________
Date Jerry B. Farley, President