Agenda Item No. _______________

Washburn University Board of Regents







SUBJECT: Change Orders - Memorial Union



DESCRIPTION:



The following change orders, which modify the contract of the contractor, are recommended.



General Contract - McPherson Contractors, Inc.

2. PR-24, PCO-32: Modify exterior handrail returns. Net increase: $1,024.00.

3. PCO-33: Additional demolition main level south (unforseen existing conditions). Net increase: $1,553.00.

4. PCO-34: Additional drywall work at upper ballroom area and main level toilet rooms. Net increase: $3,235.00.

5. PR-28, PCO-36: Add steel lintel at new masonry opening in kitchen. Net increase: $957.00.

6. PCO-35: New thermostats required where relocation of existing thermostats not possible. Net increase: $334.00.



Net contract change: Increase: $7,103.00

No change contract completion date - February 28, 2002





FINANCIAL IMPLICATIONS:



Net increase in project cost of $7,103.00. Total commitment from contingency including this request is $93,442, leaving a $286,211 contingency balance.



RECOMMENDATION:



President Farley recommends approval of the change orders by the Board of Regents.





______________________ _____________________________________

Date Jerry B. Farley, President






[ WU Home ] [ Directory ] [ A-Z Index ] [ Sitemap ] [ Contact WU ] [ Statements & Disclosures ] [ Accessibility ] [ Search ]