Agenda Item No. ____________

Washburn University Board of Regents







SUBJECT: Athletic Center Addition at Lee Arena



Project No. P-0145







DESCRIPTION:





Construction documents are being completed for the Athletic Center Addition in Lee Arena. This addition includes a large booster room, study room for athletes, coach's offices and a large conference room. Also, included is a reconfiguration of the bleachers at both ends of the court to maximize fan involvement.





Construction bids are planned for distribution on December 18, 2000 with a bid opening date of January 11, 2001. A recommendation to award a contract will be presented to the Board in January.





The construction phase is scheduled for the summer of 2001 and is to be completed in time for the 2001-2002 basketball season.









FINANCIAL IMPLICATIONS:





Construction Budget $945,000







RECOMMENDATION:





President Farley recommends the Board of Regents authorize the issuing of Construction Documents for the Athletic Center Addition at Lee Arena pursuant to the time schedule detailed previously.











__________________________ ___________________________________



(Date) Jerry B. Farley, President




[ WU Home ] [ Directory ] [ A-Z Index ] [ Sitemap ] [ Contact WU ] [ Statements & Disclosures ] [ Accessibility ] [ Search ]
© 2014 Washburn University, 1700 SW College Ave, Topeka, Kansas 66621 (785) 670-1010
Contact webmaster@washburn.edu with questions or comments.