Agenda Item No.
Washburn University Board of Regents
SUBJECT:
Re-roofing for Mabee Library.
DESCRIPTION:
This project is to replace the 24-year old roof on Mabee Library. The bids were as follows:
Contractor Base *Atl. No. 1
Vincent Roofing$102,000 - $3,000
Guilfoyle Roofing115,314 - 4,500
Weathercraft Roofing116,139 - 4,924
* Alternate No. 1 was a 3-ply roof (15-year warranty) in lieu 4-ply (20-year warranty) in base bid.
FINANCIAL IMPLICATIONS:
Expenditure of $102,000 from Capital Improvement Account 03-00302.
RECOMMENDATION:
President Farley recommends the Board of Regents approve the Award of Contract to Vincent Roofing for the base bid amount of $102,000 to re-roof the Mabee Library.
(date) Jerry B. Farley, President